Eldorado K-8 School 
 
 
Eldorado K-8 School
3351 South Indiana Street
Superior, CO 80027
720.561.4400
http://schools.bvsd.org/eldorado
Original construction date: 2000
Report Updated:  9/26/2011 
Project Details

Principal: Robyn Hamasaki

Project Manager: Tom Blahak 

Architect: RTA

Contractor: Golden Triangle Construction

Budget: $1,069,861

Eldorado K8 project expenditures

Bond Program expenditures

 

Design Advisory Team (DAT): 

Staff
Robyn Hamasaki, Principal
Jeff Van Iwarden
Laurel Reckert
Karen Fox

Meeting Schedule
Sept. 20, 27; 3:45 p.m.
Oct. 6, 3:45 p.m.
Nov. 1, 3:45 p.m.

DAT Meeting Minutes

Contact the Eldorado DAT 

Project Timeline
Scheduled Milestones
u
SD (schematic design) due 10/10; Completed 11/10
uDD (design development) drawings due 11/10; Adjusted to 1/11; Completed 1/11
uCD (construction documents) due 01/11; Completed 1/11
uBid due 01/11
uConstruction scheduled 03/11 - 08/11; Completed 08/11
 
 

u= Design phase
u= Construction bidding
u= Construction phase

Project Status

Project complete.

Project photos - September 2011

 
New classroom

 
Reading nook


New classroom 

 
New playground

 
New addition


New playground
 

 

Project photos - June 2011

 

 

 

 

 

 

 

Project photos - May 2011

 

 

 

 

 

Project photos - April 2011

 

 

 

 

 

 

Scope of Work

Facility Condition Assessment (FCA):

  • Exit signage improvements
  • HVAC improvements
  • Acoustical improvements in gyms

Program Compatibility Assessment (PCA):

  • Literacy improvements
  • Special Education improvements

Multi-Use Outdoor Facilities (MUOF):

  • Install a long jump/triple jump runway and pit (Deleted from scope. Long jumps only are installed at the high school level.) 
  • Upgrade playground surfacing, equipment, and fencing
  • Provide adequate curbing and drainage
  • Make playgrounds ADA accessible

Information Technology (IT):

  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Implement VoIP to enhance communications capabilities and reduce costs