Original construction date: 1989
Report Updated:  11/23/2011 
Project Details

Principal: Pat Heinz-Pribyl

Project Manager: Joe Gierlach 

Architect: Larson Incitti

Contractor: Bassett and Associates

Original Project Budget:

 $1,112,961

Transfer from Program Reserve to meet scope:

 $140,500

Adjusted Project Budget:  

 $1,253,461

Fireside Elementary project expenditures

Bond Program expenditures

 

Design Advisory Team (DAT): 

Staff
Pat Heinz-Pribyl, Principal
Lorraine Brooks
Mark Dayhoff
Elaine Rosquist
Carla Sanderson
Suzanne Spruce
Lynn Sullivan
Dan Wisotzkey
Francess Reda

Parents
Antonio Martinez
Jim Renwick
Tam Dalle-Molle

Community Member
Dave Mahan

Meeting Schedule

August 24, 2:45 p.m.
Sept. 7, 21, 2:45 p.m.
Oct. 12, 2:45 p.m.
Dec. 14, 2:45 p.m.

Meeting Minutes

Contact the Fireside DAT

Project Timeline
Scheduled Milestones
u
SD (schematic design) due 10/10; Completed 12/10
uDD (design development) drawings due 12/10; Completed 01/11
uCD (construction documents) due 03/11; Completed 03/11
uBid due 04/11
uConstruction scheduled 06/11 - 01/12; Under construction
 
 

u= Design phase
u= Construction bidding
u= Construction phase

Project Status
The first phase of construction including remodeling of the main office, preschool, kindergarten and kindergarten enrichment classrooms is complete. Construction of the new classroom addition is wrapping up. The rooms will be ready to occupy over winter break.  
 
 
Project photos - November 2011
 

 
New classroom addition

 
New classroom interior


New classroom interior 

 

 
Classroom interior

 

 
 
 
 
Project photos - September 2011 


Remodeled main office


New preschool room 

 

 
New kindergarten room

 
New kindergarten enrichment

 


Classroom addition

 

 

 

 
 
Project photos - June 2011

 
Office demolition

 

 
Interior demolition


Portable demolition

 

 

 

Scope of Work

Facility Condition Assessment (FCA):

  • Intercom systems improvements
  • Ventilation improvements
  • Irrigation system upgrades
  • Interior signage program

Program Compatibility Assessment (PCA):

  • Provide Special Education spaces
  • Provide small group instructional spaces
  • Provide additional staff office space

Multi-Use Outdoor Facilities (MUOF):

  • Upgrade playground surfacing, equipment, and fencing
  • Provide adequate curbing and drainage
  • Replace aged and/or unsafe playground equipment
  • Make playgrounds ADA accessible

Information Technology (IT):

  • Upgrade WAN to provide capacity to support applications with high bandwidth demands
  • Upgrade LANs to provide reliable and responsive access to data, research, and information
  • Implement VoIP to enhance communications capabilities and reduce costs